Design Plan for Steel Structure Construction Organization

Time:[2023-7-27]  Hits:2857

1、 Project Overview


Construction unit:


Project Name:


Construction unit:


Construction structure:


2、 Construction preparation


2.1 Skill Preparation

 


1. Before the official start of construction, on-site skill briefing work will be carried out in conjunction with the Planning Institute. After reviewing and positioning the guide points, a construction wire point measurement and control network will be established before the start of construction.


2. Conduct on-site verification of skill documents, familiarize yourself with the content of the documents, and based on construction investigations, promptly submit problems in the planning to the planning unit for resolution. Together, make supplementary construction drawings according to construction needs.


3. Based on the construction site investigation, planning documents, and the requirements of the owner, prepare an implementation construction organization plan, organize and guide the construction.


4. Prepare a special construction plan based on the planning documents.


5. Organize the debris, garbage, etc. within the construction site boundary.


6. Arrange a construction team to enter the site and prepare for construction.


7. Preparation of construction personnel, equipment, and materials, as well as skilled management personnel for this project, with equipment in place to meet construction requirements.


8. Do a good job of pre job training and safety education, communicate with all parties together, contact material sources, and acknowledge the transportation routes.


9. Select and implement construction teams with construction skills and experience that can ensure project quality to undertake various construction missions


2.2 Data preparation


Before leaving the factory, the steel components should be inspected by the manufacturer in accordance with the relevant specifications of the manufacturing specifications and the requirements of the planning diagram, and quality reports and actual error values should be filled out. After the steel components are delivered to the structural installation unit, the structural installation unit will conduct re inspection or spot check based on the quality report of the manufacturing plant and the classification of the components according to their properties


2. Based on the construction drawings, calculate the quantity of each main consumption data (such as welding rods, welding wires, etc.) and connecting parts (such as high-strength bolts, ordinary bolts), make order arrangements, and acknowledge the arrival time


3. After the quantity of temporary support, steel structure assembly platform, scaffolding support, safety protection, and environmental protection equipment required for each construction process is recognized, they will be arranged to enter the factory for manufacturing and installation.


2.3 Primary equipment


In steel structure construction, the main machines commonly used include: AC/DC welding machine, C02 gas shielded welding machine, Bench grinder, wire rope, rigging, Dumpy level, etc.


2.4 Operating conditions


1. The joint review of various planning plans has been completed.


Based on the structural deepening drawings, verify the stress conditions of the components during the steel structure installation, scientifically predict their possible deformation, and take corresponding reasonable technical measures to ensure the smooth operation of the steel structure installation


The review of construction plans for each special type of work has been completed.


The reinforced concrete foundation has been completed and passed the acceptance.


Temporary electricity and water supply for construction are laid in place.


6. Mobilization of labor force


7. The construction equipment and devices have passed the debugging and acceptance.


The incoming acceptance inspection of 8 components is qualified.


3、 Steel structure construction process


3.1 Process flow


Preparation of components, equipment, and personnel → Setting out and inspection of lines (axis and elevation) → Acceptance of embedded bolts and treatment of foundation surface → Component centerline and elevation line → Installation of column and beam center structure → Initial and final tightening of high-strength bolts → Welding of column to column nodes → Spot welding of beams and columns and beam joints → Scattered component (corner support) devices → Device pressed square steel → Welding and bolt connection


3.2 Operation process


1. Steel structure lifting sequence


Steel structure lifting generally requires distinguishing the lifting operation area, and steel structure lifting is carried out together in parallel order according to the distinguished area. After the lifting of a certain area is completed, measurement, calibration, and initial tightening of high-strength bolts are carried out. After several areas are installed, the overall measurement, calibration, final tightening of high-strength bolts, and welding are carried out. After welding and retesting, proceed to the lifting of the next section of the steel column. And according to the actual situation on site, carry out the lifting and partial laying operations of this laminated steel plate.


2 bolt embedment


The accuracy of the column orientation depends on the accuracy of the embedded bolt orientation. Control the elevation error of embedded bolts within+ Within 5mm, the error in positioning the axis should be controlled within ± 2mm.


3 Steel column installation process


Section 1 Steel Column Hoisting


(1) Setting of lifting points


The orientation and number of lifting points are recognized based on the specific conditions of the steel column shape, section, length, and crane function. Generally, steel columns have good elasticity and rigidity, and the lifting point adopts a single point positive lifting. The lifting point is set at the top of the column, with the column body vertical and passing through the center of gravity of the column, making it easy to lift, align, and calibrate. When multiple components are assembled into expanded units on the ground for installation, the lifting point should be accounted for and recognized.


(2) Lifting method


1. In multi-storey and high-rise steel Structural engineering, steel columns are generally lifted by a single machine, and for special or overweight components, double machines can also be used.


2. When lifting, it is necessary to keep the steel column straight and try to reverse and straighten it without dragging the root. During the lifting reversal process, attention should be paid to preventing collisions with other components that have already been lifted, and the sling should have a certain effective height. When lifting the first section of the steel column, a protective sleeve should be added to the embedded anchor bolt to avoid damaging the thread of the anchor bolt when the steel column is in place


3. The first section of the steel column is installed on the column base. Before installing the steel column, the climbing ladder and hanging basket should be hung in the predetermined position of the steel column and firmly bound. After lifting in place, the foundation bolts should be temporarily fixed and the straightness should be checked. The two sides of the steel column are equipped with temporary fixing connecting plates. After the upper section of the steel column is aligned with the center line of the lower section of the steel column top, the connecting plates are temporarily fixed with bolts.


It is necessary to wait for the anchor bolts to be fixed before loosening the sling.


(3) Steel column proofreading


Steel column proofreading requires three tasks: adjusting the elevation of the column base, adjusting the axis of the column base, and proofreading the straightness of the column body. Throughout the entire process, measurement is the primary focus.


1. Column base elevation adjustment


After placing the steel column, use the nuts or elevation adjustment blocks under the column bottom plate to control the elevation of the steel column (because some steel columns are too heavy, bolts and nuts cannot bear their weight, so a height adjustment block - steel plate adjustment elevation - needs to be added under the column bottom plate). The accuracy can be controlled within ± 1mm. The gaps reserved under the column bottom plate can be filled with high-strength, slightly expanded, and non-shortened mortar using the grouting method. When adjusting the elevation of the column base plate using nuts, the strength and stiffness of the anchor bolts should be calculated.


2. Adjustment of column bottom axis in the first section


Alignment method: Without loosening the hook of the crane, align the four points on the column base plate with the control axis of the steel column and slowly lower to the planned elevation direction.


3. Correction of Column Body Straightness in the First Section


Use cable wind rope calibration method. Use two 90 ° Theodolite to straighten. During the calibration process, continuously fine tune the nuts under the column base plate until the calibration is completed. Screw on the two nuts above the column base plate. The cable wind rope is loosened without force, and the column body is in a free state. Then recheck it with a Theodolite. If there is a slight error, repeat the above process until there is no error, and tighten the upper nuts. The nut on the anchor bolt is usually a double nut, which can be welded firmly with the screw after the nut is tightened.


Weld the nut and screw firmly.


4. Adjustment of column top elevation and control of other structural steel column elevations


There are two methods for adjusting the top elevation of columns and controlling the elevation of other structural steel columns: one is to install according to the relative elevation, and the other is to install according to the planned elevation. Generally, relative elevation devices are used. After the steel column is lifted in place, the connecting ear plates connecting the upper and lower steel columns should be fixed with large hexagonal high-strength bolts, but they should not be tightened too tightly. After being lifted by a crane, the crowbar can adjust the gap between the columns. Measure the pre calibrated elevation values of the upper and lower column tops, and after meeting the requirements, use steel wedges and spot welding to limit the drop of the steel column. Considering the welding seam and compression deformation, adjust and control the elevation error within 4mm.


5. Section 2 Steel Column Axis Adjustment


To ensure that the upper and lower columns do not show staggered joints, try to ensure that the centerline of the upper and lower columns overlaps as much as possible. The center line error of the steel column should be adjusted within a range of 3mm each time. If the error is significant, it should be adjusted 2-3 times. The positioning axis of each steel column is absolutely not allowed to use the positioning axis of the next steel column. It should be led from the ground control line to high altitude to ensure that each steel column device is correct and prevent excessive accumulation of errors.


6. Section 2 Steel Column Straightness Calibration


The key to proofreading the straightness of steel columns is to pre check the relevant dimensions of the steel columns. The straightness error at the top of the lower steel column is a comprehensive result of the bottom axis, displacement, welding deformation, sunlight effect, straightness correction, and elastic deformation of the upper steel column. Partial errors can be eliminated by reserving straightness error values. When the reserved value is greater than the accumulated error value of the next column, only the accumulated error value is reserved. Otherwise, the reserved value is reserved, and its direction is opposite to the error direction. Empirical value measurement: The general weld seam shortening value between beams and columns is less than 2mm; The shortening value of the column to column weld seam is generally 3.5mm


4. Steel beam installation process


1. Steel beam device


Steel beam devices are generally lifted using tool type lifting lugs or binding methods. Before installation, the center symbol of the steel beam should be introduced to the end of the steel beam to facilitate temporary positioning according to the positioning axis of the column bracket during lifting.


2. Calibration of steel beams


Proofreading includes elevation adjustment, vertical and horizontal axis adjustment, and straightness adjustment. It is necessary to proofread the steel structure beam after the structure forms a stiffness unit.


3. Elevation adjustment


Use a Dumpy level to stand on the beam or a specially erected platform to measure the elevation of both ends of each beam, weighted average all the data, and calculate a standard value. Calculate the elevation adjustment values of each point based on the standard values.


4. Vertical and horizontal axis calibration


Use a Theodolite to lead the axis to the column, determine the distance between the center line of each beam and the axis, pull a long rope (or use a Theodolite) on the center line of the beam top, and use a chain block to adjust the beam ends one by one. After the longitudinal and transverse axes of the steel beam meet the requirements, recheck the span of the structural beam.


5. Straightness proofreading


Straightness correction: Hang a hammer ball from the upper flange of the beam and measure the horizontal spacing between the wire rope and the upper and lower parts of the beam web. Adjust again based on the inclination of the beam (a ≠ a ') to make a=a.


6. Special rust removal equipment is used for rust removal, and shot rust removal can improve the fatigue strength and corrosion resistance of steel. The hardness of the steel surface is also improved to varying degrees, which is conducive to the adhesion of the paint film without the need for additional coating thickness. The abrasive used for rust removal must comply with quality standards and process requirements, and the relative humidity of the construction environment should not exceed 85%.


The surface of the steel after rust removal must be cleaned with tools such as a brush before proceeding to the next process. If the surface of the steel after rust removal is qualified and has returned to rust before applying primer, it needs to be re rust removed.


7. Paint


After passing the inspection of rust removal on the steel, the first layer of primer is applied on the surface. Generally, after the rust removal is completed, it is stored in the factory and can be coated within 24 hours. If stored outside the factory, the primer should be painted on duty. The paint should be applied in accordance with the planning requirements. After the first coat of primer is dry, the intermediate and top coats should be applied to ensure that the thickness of the coating meets the planning requirements. The paint should be evenly applied without sagging during the brushing process.


4、 Key points of quality acceptance


1 base and support surface


The positioning axis of the building, the positioning axis and elevation of the columns on the foundation, the specifications and orientation of the anchor bolts (anchor bolts), and the fastening of the anchor bolts (anchor bolts) should meet the planning requirements.


The fastening should meet the planning requirements.


2 Devices and proofreading


1. Steel components should comply with planning requirements and regulations. The deformation and coating detachment of steel components caused by transportation, stacking, and lifting should be corrected and repaired.


2. For nodes that require top tightening, the touch surface should not be less than 70% tight, and the maximum edge gap should not be greater than 0.8mm.


3. The surface of the steel structure should be clean, and the primary surface of the structure should be free of scars, mud, and other dirt.


When the steel component is installed on a concrete column, the error between its support center and the positioning axis should not exceed 10mm


5. Steel platforms, ladders, and railing devices in multi-layer and high-rise steel structures should comply with the current national standards of "Fixed Steel Vertical Ladders" (GB4053.1), "Fixed Steel Inclined Ladders" (GB4053.2), "Fixed Protective Rails" (GB4053.3), and "Fixed Steel Platforms" (GB4053.4).


5、 Product protection


1. High strength bolts, studs, welding rods, welding wires, etc. are stacked on shelves in the warehouse, with a maximum of four layers of stacking.


2. The stacking of steel components requires the site to be flat, sturdy, clean, dry, neatly stacked, with sleepers underneath, and to be resistant to deformation and rust.


3. It is not allowed to weld or cut completed components arbitrarily, or stack objects in the air. Welds and node plates that have been completed and inspected as qualified should be immediately sorted out and sealed as required.


When lifting the steel structure into position, it should be slowly lowered and should not collide with the already installed steel structure.


5. Carefully manage the manufactured steel columns, etc., to prevent the unreasonable placement of cushion base points from bending and deformation.


6、 Environmental and occupational health and safety control measures


1 Environmental control measures


1. When welding, steel pipes are used to set up protective railings, and colored cloth is used to surround the railings to prevent the exposure of arc light and welding smoke and dust.


2. Waste generated during and after construction should be recycled and treated.


2 Occupational Health and Safety Measures


1. It is necessary to include the safety skills and measures for operations, as well as the required equipment, in the construction organization plan of the project.


2. Corresponding responsibility systems should be established for unit project construction. Before construction, safety skill education and disclosure should be carried out step by step, and all safety skill measures should be implemented. Construction should not be carried out without implementation.


3. It is necessary to inspect the facilities and equipment used in high-altitude operations before construction, and only after acknowledging their integrity can they be put into use.


4. It is necessary for climbing and suspended operators to hold a certificate and undergo regular professional knowledge assessment and physical examination. It is necessary to wear a safety helmet, fasten a seat belt, wear anti slip shoes, and carry a tool bag when on duty.


5. The high-altitude operation area should have clear signs and be guarded by dedicated personnel. Personnel unrelated to lifting are prohibited from entering. During crane operation, no one is allowed to stand within the rotating radius of the boom.


6. When transporting lifting components, it is prohibited to stand on the components to command and place materials and tools.


7. It is necessary to bind the components firmly, and the lifting point should pass through the center of gravity of the components. When lifting, it should be stable to prevent vibration or oscillation.


8. When working at heights, safety nets need to be installed to prevent accidents caused by personnel, materials, and tools falling or flying out.


9. All objects that may fall from the construction site should be removed or fixed first. The materials used in high-altitude operations should be stacked steadily and not obstruct passage and loading and unloading.


10. When conducting high-altitude operations on rainy and snowy days, it is necessary to take reliable anti slip, cold and freezing measures. Water, ice, frost, and snow should be promptly removed. Before construction, go to the local meteorological department to understand the situation and take measures to prevent typhoons, rain, freezing, cold, and high temperatures. Before and after the snowstorm and typhoon rainstorm, the safety facilities for high-altitude operation shall be checked one by one, and the problems found shall be improved immediately.


11. During the process of structural installation, it is not allowed to operate in the same straight direction when each type of work is engaged in vertical crossing operations. The orientation of the lower level operation needs to be outside the radius of the possible falling range recognized according to the height of the upper level; When the above conditions are not met, a safety protection layer should be set up.


7、 Issues to pay attention to


The quality of pre assembled steel components should meet the planning requirements and quality specifications. The length dimensions of components such as columns, beams, and supports should include deformation values such as welding shortening allowance.


The detection of device errors should be carried out after the structure forms a spatial stiffness unit and is connected and fixed.


When installing 3 devices, it is necessary to control the construction load of the platform flooring, and the construction load must not exceed the bearing capacity of beams, deck slabs, platform flooring, etc.


Only after the installation, welding, and bolting of all components of each column are completed and accepted can the positioning axis of the previous column be measured from the ground.

Copyright:佛山市勝邦鋼結(jié)構(gòu)有限公司 Foshan Shengbang Steel Structure Co., Ltd. Record Number:粵ICP備13078463號
男人操女人逼的免费视频| 激情边亲边摸视频| 人妻超碰在线观看| 亚洲激情欧美伦理| 日韩乱码99在线视频| 成人中文字幕专区| 激情边亲边摸视频| 99久久九九社区精品| 亚洲444kkkk在线观看| 色在线观看aaa| 2020国内自拍视频| 国产一区免费在线视频观看| 青青操视频在线观看免费观看| 亚洲字幕中文精品| txtv在线视频| 国产91在线播放网址| 午夜xb福利视频| 变态另类影音资源| 亚洲美女高潮久久| 日韩中文字幕在线观看乱码| 黑丝美女被后入在线观看| 在线视频国产香蕉岛国| 欧美性欧美视频这里只有| 亚洲av免费在线播放网站| 中文av字幕在线观看一区| 美女福利视频午夜| 日韩人妻中文字幕视频| 国产精品久久久久免费播放| 天堂av中文字幕乱码免费看| 亚洲一卡2卡3卡4卡5卡| 久久精品国产亚洲av麻豆软| 91中文字幕综合| 欧美黄色aaa级| 国产精品综合不卡| 精彩av在线不卡播放| 极品在线激情av| 亚洲人妻丝袜在线观看| 国产福利精品av综合导导航| 国产一级激情黄色av| 欧美一区二区三区免费的网址| 9999在线精品| 疯狂人妻丝袜系列| 天堂av中文字幕乱码免费看| 欧美性欧美视频这里只有| 久久久久久久久久一二三| 熟女阿b老熟女一区| 青青草原国产在线精品| 欧美日一区二区三区免费在线| 黄页av在线观看| 中文字幕人妻在线| 精品人妻一区在线视频| 综合亚洲婷婷小说| 31xx日本熟女| 亚洲岛国av在线| 成人中文字幕专区| 免费观看视频成人| 亚洲成人人妻一区| 欧美经典一区二区三区| 熟女口爆吞精合集| 中文在线字幕丝袜美腿| 黄色一级成人大片| 日韩亚洲在线成人| 欧美成人金8天国加勒比| 中文字幕亚洲素人| 日本免费观看一区| 精品91久久99九九| 青青操在观看视频| 91诱惑极品美女| 国产亚洲自拍色图| 国产日韩欧美三级在线| 日韩中文乱码字幕| 999久久久蜜桃| 二区三区精品在线观看| 精品人妻交换视频在线看| 人妻视频在线免费播放| 欧美一区二区三区四区在线| 丝袜人妻诱惑在线| 在线a亚洲视频播放视频观看| 小明看看成人在线免费视频| 国产懂色av熟女丝袜精品| 97在线观看国产免费视频 | 午夜精品在线观看成人| 日韩免费黄色在线| 大香蕉伊人久久草| 久操在线免费观看视频| 美女把逼给男人操| 成年人网站在线观| 777 亚洲天堂| 国产高跟丝袜av| 国产人伦人妻亚洲| 国产强上美女在线观看| 成年人网站在线观| 亚洲 欧美 日韩 人妻在线| 另类视频免费播放观看| 玩弄丰满人妻一区二区av| 久久精品久久久久久久久久| 2020国内自拍视频| 老熟妇高潮一区二区三| 日韩精品色图在线| 3d黄色在线网站| 亚洲中文字幕视频免费在线| 在线观看大片免费网站观看| 黄色成人在线私拍| 青青爽视频免费在线观看| 偷拍亚洲另类av| 最大的黄色亚洲网站在线观看| 国产婷婷精品av在线| 亚洲午夜丝袜诱惑| 一区二区精品视频乱码| 麻豆96在线观看| 99久久九九社区精品| 欧美成人破处视频| 91精品国产一二三产区区别在哪| 最新国产精品手机网站| 香蕉国产精品久久| 人妻少妇精品在线视频| 久久少妇高潮视频免费| 精品久久国产精品久久| 精品国产露脸久久av| 在线播放一区日韩| 亚洲少妇av一区| 免费一区二区三区四区av| 日韩一区二区三区五十路人妻| 日韩av在线播放中文字幕| 色在线观看aaa| 久久午夜国产精品| 中村智惠巨乳av| 中文字幕乱码高清视频在线| 人妻精品av99| 中文字幕av人妻呻吟| 美腿丝袜综合在线日韩| 国产黑色丝袜在线| 亚洲蜜桃啪啪精品| 亚洲性感天堂欧美| 久久综合久久色鬼| 谁有av网站在线播放中文字幕| 国产欧美一区视频在线观看| 国产|九色|91| 青青操最新在线视频免费| 欧美美腿丝袜色图| 德国女人的大屁股| 国产九色91在线视频| 国产精品久久久久久av大片| 黄色一级成人大片| 日韩亚洲丝袜美腿久久| 精品人妻免费av| 99r精品视频在线播放| 最新日韩在线观看视频| 3d黄色在线网站| 久久久精品国产人妻在线观看| 国产裸体学生视频全黄网站| 3d黄色在线网站| 中文字幕欧美极品| 欧美黄色aaa级| 岛国黄色在线网站| 亚洲精品成人日本| 欧美情色伦理在线| 精品91久久99九九| 午夜激情成人在线| 青青草原vip在线视频| 黄色强奸片免费观看视频免费看 | 美女夜夜操天天干| 亚洲国产欧美另类| av伊人网好吊妞| 久久久久人妻精品一区三寸| 色婷婷激婷婷深爱五月老司机 | 熟女人妻制服丝袜中文字幕| 成人校园春色小说| 果冻亚洲国产成人av播| 色综合久久综合久久综合网| 偷拍另类激情小说| 性在线勾引户外蜜臀av| 欧美一级二级三级久久| 熟女乱一区二区三区四区| 人妻 丝袜美腿 中文字幕| 免费黄色特级大片| 午夜激情免费视频| 欧美成人破处视频| 亚洲国产美乳视频| 国产成人在线免费视频| 中文字幕福利a网| 精品毛片av一区二区三区| 国产精品久久久美女爽av| 亚洲乱码精品乱码精品中文| 日韩精品中文字幕巨臀人妻中出 | 最近的最新的中文字幕视频 | 欧美精品在线观看网址| 熟女乱一区二区三区四区| 久久国产午夜精品| 最新欧美激情一区二区| 日韩亚洲在线成人| 色在线观看aaa| 日韩超碰97在线观看| 日韩国产欧美激情在线视频| 成人精品国产一级二级| 蜜臀av在线素人人妻播放一区 | 久久久久亚洲国产av| 看久了久久久久久久久久| 2019成人在线视频| 中文字幕人妻网站| 激情人妻一区二区三区| 偷拍av高清资源| 国产人伦人妻亚洲| 极品校花口爆吞精| 亚洲成网在线观看| 中文人妻一区二区视频| 日本在线高清视频| 丝袜美腿免费在线| 国产精品亚洲欧美一级久久精品| 国内在线视频精品一区美女| 综合亚洲婷婷小说| 人妻熟妇av在线| 俺去啦视频在线精品| 精品一区二区三区 蜜臀av| 亚洲国产a∨天堂| 日韩不卡在线av| a在线视频播放免费网站| 色吧中文字幕在线| 中文字幕偷拍av| 精品在线激情av| 欧美视频亚洲视频在线观看| 国产av日韩av| 99视频在线国产观看| 亚洲视频精品一区二区三区四区| 欧美情色伦理在线| 免费一区二区三区四区av| 啪啪国产视频自拍| 日韩人妻中文字幕视频| 久久精品久久久久久久久久| 青青草原vip在线视频| 久久精品国产亚洲av麻豆软| 2020国内自拍视频| 麻豆日韩在线视频| 国产欧美在线亚洲| 成人av电影网站日韩| 四虎日韩在线观看| 爱片av在线观看| 青青草原国产在线精品| 看久了久久久久久久久久| 亚洲中文资源在线| 熟女阿b老熟女一区| 国产免费理论视频| 亚洲欧美国产免费| 久久综合亚洲狠狠伊人| 天天操天天射天天干天天爱| 女人的天堂av网| 久久久久人妻精品一区三寸| 97视频公开在线观看| 欧美视频亚洲视频在线观看| 岛国黄色在线网站| 国产网址视频在线观看| 成人黄色av在线播放| 精品毛片av一区二区三区| 最近的最新的中文字幕视频 | 国产日韩欧美高清视频一区| 青青操视频在线观看免费观看| 一区二区四区欧美| 人妻av乱片av出轨| 可以试看的黄大片| 男人天堂成人亚洲| 2025av熟女| 中文字幕欧美极品| 手机av永久免费| 日韩美女精品视频| 中国特黄免费大片| 人妻少妇精品在线视频| 黄色午夜免费网站| 人人澡人人妻人人爽少妇| 日韩亚洲在线成人| 国产老妇伦国产熟女老妇视频| sese欧美日韩| 黄色污污污免费在线观看网站| 四虎日韩在线观看| 久久成人综合亚洲精品欧美| 青青草原vip在线视频| 久久人人妻人人妻人人澡av| 人妻精品一二三区| 中文字幕av三级免费| 中文字幕日韩人妻一区| 久久精品国产亚洲av久| 国产九色91在线视频| 日韩免费黄色在线| 人妻超碰在线观看| 少妇被插激情视频| 乱码欧美中文字幕日韩| 一级国产黄片国语对白| 伦理疯狂精油按摩| 99国产小视频在线播放| 日韩一区不卡二区| 日本aaaaa级特黄大片老头| 国产欧美在线亚洲| 96国产av传媒精品| 二区三区精品在线观看| 96国产av传媒精品| 91麻豆久久国产视频| 国产免费理论视频| 青青青操国产在线视频| 国产自拍在线网站| 亚洲国产日韩不卡| 男人天堂成人亚洲| 成人av电影网站日韩| 国产婷婷精品av在线| 大香网伊人久久综合网20| 免费av资源网址| 亚洲伊人久久在线| 视频在线观看色版| 欧美av一区二区三区四区| 久久热中文在线观看| 美女网站视频大全| 欧美 成人 一区 二区| 美女网站视频大全| 欧美在线午夜观看| 激情中文字幕视频| 国产一级激情黄色av| 在线播放一区日韩| 亚洲超爽美女毛片| 岛国黄色在线网站| 国产精品久久久精品久久| 激情中文字幕视频| 东京热制服人妻诱惑| 香蕉久久久久久久av网站| 婷婷av在线免费观看| 欧美日韩少妇熟女| 91精品爽啪在线观看| 日韩中文乱码字幕| 东京热制服人妻诱惑| 噜噜视频在线播放视频| 国产一区调教在线| 青青青在线视频人视频| 欧洲免费无线码在线一区| 人妻一区两区三区四区| 亚洲视频成人在线播放| 奶头被吸得又大又黑np| 女同性恋69av| 超碰97在线在线观看| 美女激情国产精品| 国产人伦人妻亚洲| 极品人妻口爆颜射| 99热这里有国产| 88成人美女女内射| 在线 人妻 视频| 另类视频免费播放观看| 国产成人国拍亚洲精品| 青青草免费国产视频| 激情中文字幕视频| 天天干天天综合色| 精品丝袜人妻久久| 亚洲一区乱码在线观看| eeuss一区二区人妻| 日韩人妻专区一区二区| 日韩国产欧美激情在线视频| 日本免费观看一区| 香蕉国产精品久久| 国产亚洲精彩免费视频| 啪啪啪小黄片视频| 精品在线欧美日韩| 亚洲蜜桃av妇女| 好看的av网站中文字幕| 国产精品v白虎逼| 国产香蕉久久精品免费| 男人日女人的逼的视频| 色94色一区二区三区| 亚洲综合色区另类小说| 国产欧美一区视频在线观看| 亚洲欧美国产免费| 人妻av乱片av出轨| 国内在线视频精品一区美女| 亚洲中文资源在线| 女同性恋69av| 黑丝美女被后入在线观看| 国产久久精品视频在线观看| av观看视频在线| 亚洲一本一道一区二区三区| 亚洲国产长腿丝袜av天堂| 日韩中文字幕在线观看乱码| 亚洲人妻熟女一区二区三区| 深夜视频在线四区| 91亚洲精品资源| 青青草原精品视频在线观看| 超碰在线免费欧美成人亚洲| 国产一区免费在线视频观看| 国产欧美一区视频在线观看| 欧美精品在线观看网址| 精品一区二区三区 蜜臀av| 亚洲中文国产字幕| 大尺度做爰啪啪床戏欧美| 免费丝袜av二区| 搜索人妻av中文字幕| 久久少妇高潮视频免费| 青青青在线视频人视频| 中文字幕av人妻呻吟| 超碰97在线在线观看| 黑丝美女被后入在线观看| 成年人网站在线观| 亚洲成人天堂久久| 国产av专区网站大全| 日韩乱码99在线视频| 波霸肥熟女bbw| 亚洲国产天堂在线| 在线 亚洲 精品| 激情人妻一区二区三区| 中文字幕一级不卡| 熟女阿b老熟女一区| 伊人久久中文字幕av| 国产一区二区欧美视频| 尤物av在线播放| 视频在线观看色版| 激情边亲边摸视频| av完全免费在线| 成人校园春色小说| 亚洲一级做a爰片| 美女黄频蜜桃av| 国产老妇伦国产熟女老妇视频| 国产美女啪啪av| 91亚洲精品资源| 一区二区三区av资源网| 欧美成人破处视频| 国产一级激情黄色av| 人人澡人人妻人人爽少妇| 精品人妻交换视频在线看| av天堂亚洲激情| 色在线观看aaa| 中文字幕亚洲素人| 免费观看日韩一级黄色大片| 手机av永久免费| 国产经典在线播放| 亚洲 欧美 日韩 人妻在线 | 青青操视频在线观看免费观看| 日韩伦理免费大片| 熟女潮喷白浆x88av| 亚洲国产日韩不卡| 天堂男性av在线| 久久久久人妻精品一区三寸| 国产欧美成人精品久久| 激情中文字幕视频| 精品91久久99九九| 在线观看视频瑟瑟| 视色视频成人午夜精品| 一区二区三区四区av| 疯狂人妻丝袜系列| 精品人妻一区在线视频| 亚洲一卡2卡三卡| 亚洲蜜桃av妇女| 亚洲在线久久伊人| 日日操夜夜操天天高潮| 国产一级激情黄色av| 中村智惠巨乳av| 蜜臀 av 一区二区| 91精品爽啪在线观看| 国内在线视频精品一区美女| 31xx日本熟女| 91红桃在线观看| 色综合久久综合久久综合网| 深夜视频在线四区| 天堂av中文字幕乱码免费看| 亚洲精品高潮呻吟久久av| 亚洲蜜桃av妇女| 丝袜美脚av一区| 男人能不能亲女生的秘密| 欧美男女啪啪真人视频| 1024日韩精品一区二区| 中文字幕乱码视频欧美| 欧美黄色性感网站| 亚洲美女天堂av| 超碰在线免费欧美成人亚洲| 成人短视频在线版| 欧美无吗一区二区三区| 香蕉成人在线91| 把高跟丝袜美腿扛在肩上| 成人国产精品一区二区视频下载| 自拍偷拍亚洲天堂精品| 日本老熟妇ⅹxx| 中文字幕福利a网| 亚洲乱码国产乱码精品精可以看| 欧美av一区二区三区四区| 老司机中文视频网| 超碰97在线在线观看| 国产第一影院草草影院久久| 成人伊人精品色xxxx视频| 欧美情色伦理在线| 青青草免费国产视频| 谁有av网站在线播放中文字幕| 中文字幕日韩人妻一区| 成年女性午夜爽爽爽在线看片| 国产在线看片免费观看| 97精品视频在线观看免费| 中文字幕人妻熟女人妻视频| 国产美女啪啪av| 国产精品色悠悠在线观看| 中文字幕乱码高清视频在线| 天天摸天天摸天天摸| av在线一区二区三区地区| 国产视频欧美一区二区| 中文字幕偷拍av| 亚洲国产精选视频在线观看| 精品在线激情av| 亚洲精品在线观看av密乳av | 亚洲av熟妇在线| 日本在线高清视频| 东京热制服人妻诱惑| av一区二区三区久久久| 青青草原vip在线视频| 亚洲综合一区在线| 亚洲激情综合图区| 精品人妻一区二区免费| 久久久无码av一区二区三区| 中文字幕乱码视频欧美| 极品视频一区在线观看| 91精品国产一二三产区区别在哪| 中文字幕人妻熟女人妻视频| 99久久国产精品久久久久| 最近的最新的中文字幕视频| 啪啪国产视频自拍| 日韩国产欧美激情在线视频| 美女色网站在线不卡粉嫩av| 超碰97在线在线观看| 亚洲一级做a爰片| 亚洲av熟妇在线| 丝袜诱惑亚洲一区| 色在线观看aaa| 欧美极品激情一区二区三区| 午夜激情福利大片| 疯狂人妻丝袜系列| 伊人午夜综合在线观看| 亚洲 欧美 日韩 人妻在线| 在线 亚洲 精品| 日韩一区不卡二区| 国产|九色|91| 日韩不卡在线av| 小明看看成人播放平台| 亚洲福利视频天天| 三级有码在线观看| 午夜精彩视频免费观看| 中文一区二区三区在线播放| 制服丝袜亚洲另类| aise美乳诱惑| 在线看成人a v| 成人日韩亚洲欧美| 久久精品国产亚洲av麻豆软| 精品欧美日韩免费| 成人动漫在线观看播放| ysl蜜桃棕调色| 国产九色91在线视频| 中文字幕成人乱码不卡视频| 国产九色91在线视频| 在线a亚洲视频播放视频观看| aise美乳诱惑| 成人欧美三级视频| 蜜臀av在线素人人妻播放一区| 欧美一区二区三区四区在线| 中文av字幕在线观看一区| 亚洲在线久久伊人| 亚洲天堂国产精品区| 极品人妻口爆颜射| 伊人av在线播放| 观看国产精品97视频| 91国自产精品一区二区三区| 亚洲综合自拍成人偷拍网站| 一区二区三区四区av| 亚洲在线久久伊人| 老熟妇高潮一区二区三| 美女激情国产精品| 人妻视频在线免费播放| 自拍偷拍亚洲天堂精品| 天天干天天综合色| 国产老熟露脸对白| 青青操最新在线视频免费 | 日韩av在线播放中文字幕| 自拍偷拍美腿丝袜亚洲| 自拍偷拍亚洲天堂精品| 亚洲欧美国产免费| 青青草原国产在线精品| 韩国女主播青草完整视频| 青青在线观看视频精品| sese欧美日韩| 国产伦理精品av| 国产熟女一本区三区四区| 国产精品偷伦免费视频| 欧美无吗一区二区三区| 国产第一影院草草影院久久| 免费黄色特级大片| 淫妇天天干夜夜操| 在线观看视频瑟瑟| 出轨少妇自白小说| 999久久久蜜桃| 91国自产精品一区二区三区| 人妻人伦精品国产| 巨乳中文字幕一区| 亚洲丝袜美女诱惑| 亚洲一区乱码在线观看| 国产精品久久久久久av大片| 看久了久久久久久久久久| 精彩视频久久久久| 91精品视频在线观看免费版| 1024人妻熟女一区二区三区| 日韩美女精品视频| 天天综合天天精品| 中文字幕亚洲天堂| 亚洲天堂嗯啊嗯啊| 在线观看大片免费网站观看| 亚洲美女高潮久久| 精品丰满少妇人妻| 久久精品久久久久久久久久| av一区二区三区久久久| 人妻视频在线免费播放| 淫妇操BBB操BBB操BBB| 亚洲人妻熟女一区二区三区| 丝袜诱惑亚洲一区| 国产精品人妻在线| 亚洲超爽美女毛片| 欧美三级在线免费观看| 网页端在线聊天室| 久碰久摸久看在线观看| 疯狂人妻丝袜系列| 岛国黄色在线网站| 极品人妻口爆颜射| 欧美亚洲第28页| 成人黄色av在线播放| 暖暖视频高清在线观看中文| 亚洲人妻丝袜在线观看| 亚洲av网址观看| 欧洲免费无线码在线一区| 最全同人动漫网址| 男人日女人的逼的视频| 激情欧美在线激情| 亚洲国产精选视频在线观看| 日韩 激情 美乳| 日韩不卡在线av| 国产卡一卡二专区| 国产麻豆黄色大片| 大香网伊人久久综合网20| 国产av高潮大全| 欧美精品在线观看网址| 凹凸视频一二三区在线观看| 日韩在线高清视频一区二区| 美女把逼给男人操| 日韩国产成人一区| 91亚洲精品资源| 美女把逼给男人操| 爱片av在线观看| aaa级欧美黄片| 亚洲天堂国产精品区| 另类视频免费播放观看| 欧美情色伦理在线| 二区三区精品在线观看| 19国产精品麻豆| 久久久久久久美女特黄大片| 国产精品久久久精品久久| 午夜一级免费福利视频| 午夜精品在线观看成人| 精品欧美日韩免费| 青青操在观看视频| 成人精品一区二区三区的电影| 色在线观看aaa| 亚洲精品人成网址| 日韩人妻专区一区二区| 精品免费污污网站在线观看| 国产亚洲自拍色图| ff14一区二区三区分别是啥| 巨乳中文字幕一区| 超碰在线成人97| 俺去啦视频在线精品| 疯狂人妻丝袜系列| 伊人av在线播放| 天天操天天射天天干天天爱| 国产一区二区在线激情欧美| av影音在线不卡| 超碰在线成人97| 大尺度做爰啪啪床戏欧美| 变态另类影音资源| 国产裸体一二区三区视频| 精品av综合一区二区三区| 日本精品一区二区三区在线精品| 激情中文字幕视频| 国产精品久久国产丁香花| 国产一区二区三区女人的床叫声| 中文人妻熟妇精品乱又伧不卡| av天堂亚洲激情| 国产人伦人妻亚洲| 青青青青啪啪啪啪网站| 日韩免费三级视频| 午夜熟女经典一区二区| 欧美黄色aaa级| 萌白的所有视频在线观看| 日本老熟妇ⅹxx| 在线a亚洲视频播放视频观看 | 精品丰满少妇人妻| 美女色网站在线不卡粉嫩av| 四虎av在线观看| eeuss一区二区人妻| 亚洲欧美精品卡一卡二卡三| 午夜xb福利视频| 日韩精品色图在线| 免费观看日韩一级黄色大片| 美女把逼给男人操| 日韩一区二区三区五十路人妻| 成人日本免费视频| 小明看看成人播放平台| 人妻一区两区三区四区| 国产熟女av一区| 亚洲美女高潮久久| 国产99丝袜诱惑| 性感丝袜美女诱惑| 免费看插b视频网站| 超碰九七在线免费观看| 那个小区的人妻在线观看| 亚洲av变态另类| 久久日韩美女人妻精品| 凹凸视频一二三区在线观看| 中文字幕日韩人妻一区| 国产精品最新自拍| 青青视频成人免费完整版| 91 亚洲 在线| 超碰在线免费欧美成人亚洲| 日本五十路熟女网| 深夜视频在线四区| 日韩一区不卡二区| 大香蕉伊人久久草| 久久国语露脸精品国产麻豆| 欧美情色伦理在线| 人人澡人人妻人人爽少妇| 欧美情色免费视频| 丝袜美腿诱惑福利| 亚洲中文字幕乱码七糟| 熟女口爆吞精合集| 99久久九九社区精品| 亚洲一卡2卡3卡4卡5卡| 淫妇天天干夜夜操| 麻豆96在线观看| 激情内射一区二区三区| 成人精品一区二区三区的电影| 免费观看性感美女| 极品视频一区在线观看| 淫妇天天干夜夜操| 不卡的av中文字幕在线观看| 熟妇 人妻 中文| 亚洲成av人片一区二区久久久| 美女把逼给男人操| 国产免费理论视频| 日本老熟妇ⅹxx| 最新国产激情视频| 亚洲国产天堂在线| 亚洲乱码精品乱码精品中文| 亚洲中文资源在线| 二区三区精品在线观看| 色综合久久综合久久综合网| 亚洲不卡免费在线| 淫妇操BBB操BBB操BBB| 国产91在线播放网址| 日韩亚洲丝袜美腿久久| 日韩精品中文字幕巨臀人妻中出| 成年女性午夜爽爽爽在线看片| 久久成人综合亚洲精品欧美| 在线a亚洲视频播放视频观看| 伊人久久婷婷综合五月97色 | 亚洲 欧美 日韩 人妻在线| 国产精品久久久精品久久| 视频在线观看色版| 91精品人妻呻吟| 亚洲综合色区另类小说| 女人的天堂av网| 女同性恋69av| 日韩人妻少妇中文字幕| 一区二区精品视频乱码| 中文人妻熟妇精品乱又伧不卡| 粉嫩av在线综合| 四十路g五十路熟女豊满av| 91精品视频在线观看免费版| 日本五十路熟女网| 亚洲女人av在线| 少妇被插激情视频| 国产在线视频观看| av影音在线不卡| 青青电视剧全集免费观看| 亚洲超爽美女毛片| 美女扒开逼逼让男人操| 亚洲精品亚洲成人| 鸿观全集在线观看视频| 看久了久久久久久久久久| 97在线视频在线激情| 亚洲视频成人在线播放| 红桃在线观看av| 午夜激情免费视频| 久久av一区二区三区neco| 国产精品黄视频免费看| av观看视频在线| 久久国产午夜精品| 香蕉成人在线91| 国产一区二区欧美视频| 欧美情色伦理在线| 最新日韩在线观看视频| 国产av激情国产熟女| 中文一区二区三区在线播放| 欧美精品在线观看网址| 日韩中文乱码字幕| 亚洲中文av字幕综合| 欧美在线午夜观看| 日韩丝袜情趣美女图片| 19国产精品麻豆| robolox涩涩的视频免费看| 午夜熟女经典一区二区| 天天操天天射天天干天天爱 | 中文人妻一区二区视频| 超碰在线成人97| 午夜xb福利视频| 国产精品欧美日韩精品| 97视频在线播放| 国产久久精品视频在线观看| 99精品综合在线视频| 久久凹凸视频在线观看| 999久久久蜜桃| 深夜激情小视频在线观看| 大片福利网站导航| 国产视频97在线播放| 三级有码在线观看| 果冻亚洲国产成人av播| 97在线观看国产免费视频| 亚洲av综合av一区二区综| 精产国品一二三产品区别在| 日本aaaaa级特黄大片老头| 久久久蜜桃成人网| 亚洲国产a∨天堂| 欧美三级免费观看一区二区| 一级片一级黄色片| av影音在线不卡| 人妻中文字幕精品| 亚洲av色图网站| 国产精品人妻激情| 亚洲 欧美 另类 丝袜| 人妻av乱片av出轨| 性感美女黄色刺激视频| 二区三区精品在线观看| 亚洲中文av字幕综合| 中文字幕人妻网站| 成人亚洲自拍一区| 自拍视频在线观看一区| 老熟妇高潮一区二区三| 视频一区二区蜜桃| ysl蜜桃色14| 亚洲中文av字幕综合| 萌白的所有视频在线观看| av网站国产在线| 无人区午夜精品乱码一区二区| 精品熟女人妻在线视频| 国产av专区网站大全| av影音在线不卡| 国产精品岛国久久久久久| 天天色天天干网址| 1024人妻熟女一区二区三区| 亚洲av黄久久久| 麻豆日韩在线视频| 91在线精品在线| 99久久免费精彩视频| 亚洲乱码精品乱码精品中文| 黄黄的视频靠在线观看| aaa级欧美黄片| 精品国产露脸久久av| 久操在线免费观看视频| 最新欧美激情一区二区| 中国特黄免费大片| 91精品国产一二三产区区别在哪| 国产av高潮大全| 午夜免费观看国产视频| 88成人美女女内射| 久久成人综合亚洲精品欧美| 亚洲福利视频天天| 五月婷中文字幕网| 夜夜嗨av老熟女一区二区三区| 久久久99久久久蜜桃| 国产一级激情黄色av| 亚洲av色图网站| 美女把逼给男人操| 日本人妻乱子免费播放| 97视频都是精品| 黄片激情在线观看| 国产精品久久久久久av福利| 女人的天堂av网| 最新欧美激情一区二区| 88成人美女女内射| 熟女人妻制服丝袜中文字幕| 中文人妻一区二区视频| 国产裸体一二区三区视频| 欧美日韩少妇熟女| 亚洲青青青草在线免费视频| 骚逼被大鸡吧插视频| 国产情侣自拍成人| 欧美黄色激情一区二区|